Victorian Rentals 2027: Gas to Electric Rules
There's a lot of noise about Victoria's 2027 rental standards, and most of it overstates what's actually happening. So let's be precise about it.
From 1 March 2027, new minimum energy efficiency standards begin to phase in for Victorian rental properties. They build on the minimum standards that have applied since 2021 and the 2-star heating standard introduced in 2023.
Key points
- The heating and hot water requirements are triggered by failure, not by a calendar date — a working gas appliance can stay.
- After 1 March 2027 a failed gas hot water system cannot be replaced with another gas unit.
- All Victorian rentals need fixed efficient electric cooling in the main living area by 1 July 2030.
- One reverse cycle system in the main living area can satisfy both the heating and cooling standards.
The most important thing: it's triggered, not scheduled
You do not have to remove a working gas appliance on 1 March 2027.
The heating and hot water requirements are triggered by failure. When an existing system fails and cannot be repaired, the replacement must be electric. A functioning gas heater or gas hot water unit can stay exactly where it is, and you can still repair it.
That's the headline, and it's the part most landlords have wrong in one direction or the other — either panicking about a wholesale replacement bill, or assuming nothing applies to them.
Heating
Trigger: the existing heating system fails and cannot be repaired. Requirement: replacement with an efficient electric system — a reverse cycle air conditioner in the main living area.
Note that the existing standard already applies today, regardless of 2027: every rental must have a fixed, energy-efficient heater in the main living area. A portable heater does not satisfy it. If a property currently has no fixed heating, that's a live obligation now, not a 2027 one.
Hot water
Trigger: the existing hot water system fails and cannot be repaired. Requirement: an electric heat pump hot water system.
This one has a harder edge to it. After 1 March 2027, a failed gas hot water system cannot be replaced with another gas unit. Like-for-like is no longer an option. If the existing system is working, no action is required.
Cooling — and the one hard date
Cooling works differently, and this is the deadline to put in the diary.
From 1 March 2027, the cooling standard is generally triggered at the start of a new rental agreement, when an agreement converts to periodic, or when existing fixed cooling fails and can't be repaired.
But there's also a portfolio-wide backstop: by 1 July 2030, every Victorian rental needs fixed, efficient electric cooling in the main living area — whether or not a new lease has started.
In practice, most properties will hit the trigger through ordinary tenant turnover well before 2030. The 2030 date catches the long-term tenancies that haven't turned over. If you hold properties with stable, multi-year tenants, those are the ones that will still be sitting there in 2030 needing work.
The detail worth acting on: one appliance, two standards
Here's the part that changes the maths.
A reverse cycle air conditioner is an efficient electric heater and an efficient electric cooler. Installed in the main living area, one unit can satisfy both the heating requirement and the cooling requirement.
Consumer Affairs Victoria's own guidance for property managers makes this point — when a heater needs replacing, it's worth considering whether a reverse cycle system could cover both obligations.
So if you're facing a failed gas heater in 2027, the choice isn't really "electric heater or gas heater." It's whether you spend once and clear two standards including the 2030 cooling backstop, or spend twice.
What isn't included
Gas cooktops. There's no requirement to convert stovetop gas cooking to electric. It's encouraged, not mandated.
The rest of the package
The 2027 standards cover more than appliances. In broad terms they also address ceiling insulation where none exists, draughtproofing (from 1 July 2027), and 4-star WELS showerheads, generally triggered at the start of a new rental agreement. Those aren't our trade, but they're part of the same compliance picture and worth scoping at the same time.
Why waiting for the failure is the expensive strategy
The rules let you wait. Waiting is still usually the wrong call, for reasons that have nothing to do with compliance.
Gas heaters fail in July. They fail on the coldest week of the year, because that's when they're working hardest. That's also the week every HVAC company in Melbourne is fully booked and your tenant is in a property with no heating — which is an urgent repair obligation with a clock on it.
Emergency replacement is the worst price you'll ever pay. No time to compare quotes, no time to plan the installation, and whatever's in stock is what you're getting.
Some properties aren't electrically ready. Switchboard capacity, available circuits, an old fuse box, or supply limitations can turn a straightforward changeover into a much bigger job. That's a problem you want to discover during planning, not at 4pm on a Friday in July with a tenant waiting.
Rebates take a moment to arrange. Doing it properly under the VEU program means paperwork and an accredited provider. Doable in an emergency, but not ideally.
Rebates
The Victorian Energy Upgrades program provides discounts for exactly these upgrades — replacing a gas space heater with a reverse cycle air conditioner, and replacing gas hot water with a heat pump water heater. There's also a separate Solar for Rentals rebate for landlords, and discounts for draughtproofing and showerheads.
Two things to know. The discount comes off the invoice through an Accredited Provider rather than arriving as a payment. And it applies once to a given upgrade — so it's worth getting the equipment decision right the first time.
What we'd suggest doing now
- Audit the portfolio. Which properties have gas heating, gas hot water, no fixed cooling, or no fixed heating at all?
- Flag the old units. Anything over about 12–15 years is a candidate to fail inside the window. Those are your planned replacements.
- Check the fixed heating standard today. That one already applies.
- Identify long-tenancy properties. They're the ones that will still need cooling in 2030 without a lease trigger to force it earlier.
- Check electrical readiness on anything you'd be converting from gas.
- Plan replacements for summer and autumn, not mid-winter.